PPL Electric Utilities moves into new phase of Scranton transmission line rebuild project
DECEMBER 2, 2010
PPL Electric Utilitiessaid it is moving into a new phase of the transmission line replacement project in Scranton that began earlier this year. The company is in the midst of rebuilding three older transmission lines in the City of Scranton as part of an ongoing, longer-term regional plan to strengthen the aging electric infrastructure and ensure reliability for area customers.
The $7 million Stanton-Providence project began in April and will likely be completed in spring 2011. Built more than 70 years ago, the line was in need of replacement to meet the current and future electric needs of the city.
The project involves replacing eight miles of existing 69-kilovolt power lines with new utility poles and upgrades to the two local substations that supply power to part of the Scranton community, primarily east of Route 11. We’ll also be making upgrades to local distribution facilities in the area to improve service.
The construction does not involve installation of a new power line, like the planned Susquehanna-Roseland transmission line linking Pennsylvania and New Jersey. It is a replacement of existing lines that will operate at the same voltage as they have since the 1940s. And there are no plans to raise the voltage level of the lines.
Overall the company is taking down 70 old wooden structures and replacing them with similar wooden utility poles along the same utility right of way. In limited cases, steel structures are being installed for extra strength and durability. All of the new poles are somewhat higher, about 10 to 20 feet, to conform to modern electrical code. PPL Electric Utilities is working with other utilities as well to transfer telephone and cable facilities from the old structures to the new poles.
“We want to thank local property owners for their cooperation during the past several months of the project. We will continue to notify neighbors of the line as work is planned near your property. And we’ll be sure to restore conditions once work is completed,” said project manager Mike Hasel.
More User Press Releases
- 2010 Corporate Sustainability Report highlights PPL Corporation’s commitment to community, environment and safety
- Deadline nears for E-power renewable energy rebate program
- PPL Electric Utilities plans new substation to serve east-central York County
- Annual meeting date set by PPL Corporation
- Senior banking executive named to PPL Corporation board
- PPL completes sale of remaining hydroelectric assets in Maine to river restoration trust
- Pennsylvania Public Utility Commission approves PPL Electric Utilities rates for 2011
- National report shows Pennsylvanians benefit from electric choice
- Appliance recycling program exceeds 15,000 mark in its first year for PPL Electric Utilities
- Tips to stay safe and save energy this holiday season from PPL Electric Utilities
Like this site on Facebook
Distribute Press Release
- Post press release to 50+ free press release websites.
- Send to 100+ online publications.
- Effortlessly publish all your press releases with our automated pickup and submission service.
Shopping cart
User login
Search
Bookmark/Search this post
Primary Menu
- News by Region
- Business
- List of Industries
- Technology
- Aerospace & Defense
- Agriculture & Forestry
- Arts
- Automotive
- Business Services
- Chemicals
- Construction & Maintenance
- Consumer Goods
- Education
- Electrical & Electronics
- Energy
- Entertainment
- Food & Related Products
- General Business
- Government
- Healthcare
- Heavy Industry
- Home
- Industrial Goods & Services
- Industrial Materials
- Medical
- Mining & Drilling
- Publishing & Printing
- Retail
- Society
- Sports
- Supermarkets
- Telecommunications
- Textiles & Nonwovens
- Transportation & Logistics
- Travel & Hospitality
- Wholesale